James Garner Avenue Phase III







James Garner Phase III consists of reconstruction of James Garner between Duffy Street and the recently constructed intersection at Acres Street, near the new Norman Central Library.
The project will provide for a new roadway and parking layout, new signals at the Main Street intersection and improved pedestrian facilities with new ADA compliant sidewalks and signalized crossings.
Projected Schedule
Begin Right of Way Acquisition and Utility Relocations - October 2022
Final Plans, Specifications, and Estimates - March 2024
Open Bids - March 2025
Begin Construction - May 2025
Complete Construction - May 2026